Quick Search


Tibetan singing bowl music,sound healing, remove negative energy.

528hz solfreggio music -  Attract Wealth and Abundance, Manifest Money and Increase Luck



 
Your forum announcement here!

  Free Advertising Forums | Free Advertising Board | Post Free Ads Forum | Free Advertising Forums Directory | Best Free Advertising Methods | Advertising Forums > Other Methods of FREE Advertising > Safelist Directory

Safelist Directory Safelists will also work if you use them. The bigger the list the better isn't always true... sometimes the smaller lists can be just as responsive if not more. It all depends on you and your dillegence.

Reply
 
Thread Tools Search this Thread Display Modes
Old 03-30-2011, 10:10 AM   #1
mbft7as10
Sergeant
 
Join Date: Mar 2011
Posts: 57
mbft7as10 is on a distinguished road
Default puma trainer 7557

Why Projects Fail? Part 4
Project management frameworks in practice: the C-NOMIS case study
This article deals with the fourth of the OGC��s eight causes of project failure: poor approach to project and risk management.
The OGC, in consultation with hundreds of experienced management professionals and business experts, has developed best practice guidelines and frameworks for project management and risk management. PRINCE2, the project management methodology,puma trainer, has become the de-facto standard throughout the UK government, and is the most widely recognised industry qualification in Europe. M_o_R (Management of Risks) provides a similarly standardised approach for understanding and handling the risks to an organisation or a project.
Considering the bedrock of project and risk management support and advice that the C-NOMIS project could fall back on, how did the absence of a solid approach to project/risk management become one of the key factors that the NAO identified in the failure of the project?
The NAO report highlighted several specific flaws in the approach to project and risk management used on the C-NOMIS project:
* Over-reliance on contract staff
Due to a shortage in skilled personnel, the C-NOMIS project relied too much on contract staff, which led to higher costs,cheap puma trainers, more time spent inducting staff into the project and less staff ��buy-in�� on the project.
* Inexperienced SRO (Senior Responsible Owner)
The SRO takes personal responsibility for the delivery of the project and any proposed business changes. The first SRO on the C-NOMIS project had little experience of managing large-scale IT projects, and therefore was perhaps ill-equipped to deal with the scope creep that allowed the budget to soar and the estimated duration of the project more than double.
* Risks identified but not properly managed
Although it was recognised early on that the C-NOMIS project was high-risk, there was no contingency budget for implementing risk responses.
* Scope creep
Poor change management procedures led to the incorporation of many adjustments and additions into the original product specification. These changes eventually proved too much for the time and budget allocated to the project, and C-NOMIS overran its tolerance levels.
* ��Good news�� culture
The project manager was the key person reporting to the programme director, which led to a ��good news�� culture and an absence of external quality assurance on the project. This,nike air shox shoes, combined with the infrequency of project-programme communications meant that senior management staff were not aware of the scale of the problems on the C-NOMIS project.
Summary and solutions
* Ideally, a project management team should remain consistent for the duration of the project. While changes in staff at lower management levels do not usually give rise to a project issue, it is something that should be monitored and, if possible,christian louboutin website, avoided. Changes to corporate/programme staff can also usually be absorbed by a solid project management framework.
However, changes to senior project management staff (such as the SRO or the project manager) will require the investment of time and resources, as these roles form the links between the different levels of project activity.
* It is not mandatory for senior project management staff to have technical experience in the type of projects that they manage. Indeed, sometimes specialists have more difficulties viewing the project in terms of products rather than activities, and provide less adept than the non-specialists.
However, the C-NOMIS project was reliant to a large degree on the delivery of a complex information management system. The project failed, to a substantial extent, because it underestimated the cost and complexity of the system. An experienced IT project manager, or an experienced project manager equipped with lessons learned on previous major IT projects, might have been better positioned to judge and enforce the scope tolerance on the project and deal with IT suppliers.
* Every project should have external assurance, particularly a project with such a high profile (and such a high budget! ) as the C-NOMIS project. Without project assurance it is impossible for the corporate/programme management levels to be certain that the project is making adequate progress �C as illustrated by the example of C-NOMIS.
* Too few senior managers understand project management and there is reluctance by these people to attend PRINCE2 training by these people. This is a serious problem that senior managers need to address. Project management frameworks such as PRINCE2 cannot be expected to work if the role assigned to senior management is not performed properly. My recommendation would be to send senior managers on PRINCE2 courses!
Looking ahead ��
A poor approach to project and risk management undermined the C-NOMIS project. In my next post I am going to examine the fifth of the OGC causes of project failure �C too little attention paid to breaking down the project into manageable stages.
Topics related articles:


buy mbt shoes 6364

discount tory burch 5113

buy vibram shoes 6335
mbft7as10 is offline   Reply With Quote

Sponsored Links
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off


All times are GMT. The time now is 04:59 AM.

 

Powered by vBulletin Version 3.6.4
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Free Advertising Forums | Free Advertising Message Boards | Post Free Ads Forum